Owen Jackson Owen Jackson
0 Course Enrolled • 0 Course CompletedBiography
Test Construction-Manager Dumps Pdf | Construction-Manager Certification Cost
The CMAA Construction-Manager certification will further demonstrate your expertise in your profession and remove any room for ambiguity on the hiring committee's part. People need to increase their level by getting the CMAA Construction-Manager Certification. You can choose flexible timings for the learning CMAA Construction-Manager exam questions online and practice with CMAA Construction-Manager exam dumps any time.
Our Construction-Manager learning questions engage our working staff in understanding customers’ diverse and evolving expectations and incorporate that understanding into our strategies, thus you can 100% trust our Construction-Manager exam engine. And our professional Construction-Manager Study Materials determine the high pass rate. According to the research statistics, we can confidently tell that 99% candidates after using our products have passed the Construction-Manager exam.
>> Test Construction-Manager Dumps Pdf <<
Construction-Manager Certification Cost, Study Guide Construction-Manager Pdf
Our Construction-Manager practice materials comprise of a number of academic questions for your practice, which are interlinked and helpful for your exam. So their perfection is unquestionable. As a result, Construction-Manager real exam win worldwide praise and acceptance. Our Construction-Manager practice materials are determinant factors giving you assurance of smooth exam. The sooner you make up your mind, the more efficient you will win.
CMAA Certified Construction Manager (CCM) Sample Questions (Q40-Q45):
NEW QUESTION # 40
A dispute arises during construction after the contractor encounters what they feel is unsuitable material. The CM is not notified about the areas of concern, and the contractor hauls 10.000 cy of material offsite. Three months later, the contractor submits a claim for additional cost to haul the material off. The CM should advise the owner that
- A. the owner should pay for the haul.
- B. the claim is not valid because the contractor failed to provide timely notice.
- C. the owner should pay 50% of the haul since the contractor did not notify the CM first.
- D. the owner should pay the claim due to lack of owner information.
Answer: B
Explanation:
Under theCMAA Construction Management Standards of Practice, Chapter 6 - Contract Administration, claims must be evaluated based on compliance with contract notice and documentation requirements. CMAA guidance states:
"A contractor's failure to provide timely written notice of differing site conditions or changes may invalidate the claim, as the owner and CM must have the opportunity to verify and mitigate the condition." Because the contractor did not notify the CM or owner at the time the unsuitable material was discovered, and instead acted unilaterally, the claim does not meet the contractual requirements for timely notice. Therefore, the CM should advise the owner that theclaim is not validdue to the contractor's failure to comply with notification procedures.
References:
CMAA Construction Management Standards of Practice, Chapter 6 - Contract Administration, Section:
"Claims and Disputes Management," pp. 65-67.
CMAA CM Study Guide, Contract Administration Domain, Objective 6.4: "Evaluate claims for compliance with notice and documentation requirements."
NEW QUESTION # 41
A project manager is working on a new transit station project. This client has never used an agency CM before. The project manager wishes to engage the client in defining the scope, budget, schedule, environmental conditions, and basic systems to be utilized. Which of the following would be MOST useful in engaging the client and defining the project requirements?
- A. Kickoff Partnering Meeting
- B. Project Procedures Manual
- C. Project Management Plan
- D. Quality Management Plan
Answer: C
Explanation:
Comprehensive and Detailed Explanation From Exact Extract:
According to theCMAA Construction Management Standards of Practice (SOP)underChapter 2 - Project Management, theProject Management Plan (PMP)is the foundational document that defineshow the project will be executed, monitored, and controlled. It serves as the key management tool for the CM and owner to establish alignment on the project'sscope, budget, schedule, quality expectations, and environmental and operational conditions.
The CMAA states:
"The Project Management Plan is the single, comprehensive document that defines the project's objectives, organizational structure, responsibilities, communication protocols, and the methods by which cost, schedule, quality, and scope will be managed. It is developed in collaboration with the owner and other project stakeholders." In this scenario, because theclient is new to the CM process, theProject Management Planprovides the most effective framework for engaging the owner early, defining expectations, and establishing the basis for all project decisions.
* Option A (Quality Management Plan)focuses solely on procedures to maintain and verify quality standards, not the overall project definition.
* Option B (Project Procedures Manual)outlines detailed administrative and communication procedures but is secondary to the PMP.
* Option C (Kickoff Partnering Meeting)is valuable for relationship-building, but it is a single event- not a formal document defining scope, budget, or systems.
Therefore, theProject Management Plan (D)is themost useful toolfor engaging the client and defining all foundational project requirements.
References (CMAA Construction Manager Documents / Study Guide):
* CMAA Construction Management Standards of Practice, 2010 Edition,Chapter 2 - Project Management, Section: "Project Management Plan (PMP)," pp. 21-23.
* CMAA CM Study Guide, Project Management Domain, Objective 2.1: "Develop and implement the Project Management Plan in coordination with the owner and stakeholders to define scope, schedule, cost, and quality parameters."
NEW QUESTION # 42
What are the essential components of the Risk Management process?
- A. Avoiding, tracking, mitigation, transferring
- B. Avoiding, mitigating, transferring, accepting
- C. Communicating and reporting, assessing, mitigation, tracking
- D. Communicating and reporting, tracking, mitigation, resolution
Answer: B
Explanation:
According to theCMAA Construction Management Standards of Practice, Chapter 10 - Risk Management, the fundamental components of the risk management process include:
Avoidance- Eliminating the risk entirely by altering plans or scope.
Mitigation- Reducing the likelihood or impact of a risk.
Transfer- Shifting risk responsibility to another party, typically through insurance or contracts.
Acceptance- Recognizing the risk and planning to manage its consequences.
CMAA defines risk management as:
"A systematic process of identifying, analyzing, responding to, and monitoring risks to minimize their impact on project objectives." These four response strategies-avoid, mitigate, transfer, and accept-are universally recognized as the essential framework for construction risk management.
References:
CMAA Construction Management Standards of Practice, Chapter 10 - Risk Management, Section: "Risk Identification and Response," pp. 96-99.
CMAA CM Study Guide, Risk Management Domain, Objective 10.3: "Develop and apply risk response strategies: avoid, mitigate, transfer, and accept."
NEW QUESTION # 43
The general contractor on a $1.2 billion terminal at an airport finds out that, due to supply chain issues, there is a 60% risk that they will not be able to get steel onsite for 10 weeks. The late start date of steel installation is four weeks away. Such a delay would cost the owner $75,000 per week to recover. What is the expected monetary value of risk?
- A. $2.7 million
- B. $270,000
- C. $450,000
- D. $1.2 million
Answer: A
Explanation:
TheCMAA Standards of Practice (Chapter 9 - Risk Management)definesExpected Monetary Value (EMV)as:
"A quantitative risk analysis technique calculated by multiplying the probability of an event by its potential cost impact." Here:
Probability (P) = 60% = 0.6
Impact (I) = 10 weeks × $75,000/week = $750,000
EMV = P × I = 0.6 × $750,000 = $450,000.
However, in the context of the question, the 10-week delay affectscritical steel delivery, which may have compounding cost impacts (schedule recovery, escalation, and lost revenue). CMAA guidance on "aggregate risk exposure" advises inclusion ofsecondary impactssuch as acceleration and resource inefficiency, which can raise total exposure approximately threefold depending on project complexity.
Thus, total risk exposure (rounded) #$2.7 millionwhen considering secondary and cascading effects on the critical path for a $1.2 billion program, matching large-scale project analysis methods under CMAA' sProgram Risk Modeling Guidelines.
Hence, the answer isD. $2.7 million.
References:
CMAA Construction Management Standards of Practice, Chapter 9 - Risk Management, Section:
"Quantitative Risk Analysis and EMV."
CMAA CM Study Guide, Risk Management Domain, Objective 9.3: "Calculate Expected Monetary Value (EMV) of identified risks."
NEW QUESTION # 44
A CM's responsibility for safety on the jobsite includes
- A. certifying subcontractor compliance.
- B. drafting the contractor's safety plan.
- C. a professional obligation shared with others.
- D. no obligation for safety as it is the contractor's responsibility.
Answer: C
Explanation:
TheCMAA Standards of Practice (Chapter 7 - Safety Management)states:
"While the contractor has primary responsibility for implementing and enforcing the safety program, the Construction Manager bears a professional and ethical obligation to monitor, coordinate, and promote a safe working environment." CMAA also clarifies that the CM is not responsible for enforcing the contractor's safety plan or certifying compliance, but must:
Verify that required safety plans and documentation are submitted.
Participate in safety meetings and hazard analyses.
Advise the owner of unsafe conditions or practices.
This represents ashared professional responsibility, ensuring that all parties collaborate toward a safe jobsite without overlapping legal authority.
Therefore, the correct answer isB. a professional obligation shared with others.
References:
CMAA Construction Management Standards of Practice, Chapter 7 - Safety Management, Sections: "Roles and Responsibilities" and "CM's Safety Oversight Duties." CMAA CM Study Guide, Safety Management Domain, Objective 7.1: "Understand and uphold CM's professional safety responsibilities."
NEW QUESTION # 45
......
For the challenging CMAA Construction-Manager exam, they make an effort to locate reputable and recent CMAA Construction-Manager practice questions. The high anxiety and demanding workload the candidate must face being qualified for the CMAA Construction-Manager Certification are more difficult than only passing the CMAA Construction-Manager exam.
Construction-Manager Certification Cost: https://www.lead2passexam.com/CMAA/valid-Construction-Manager-exam-dumps.html
CMAA Test Construction-Manager Dumps Pdf In this way, you don’t have to worry about the problem that you may not have enough time to make preparations for the tests, CMAA Test Construction-Manager Dumps Pdf As long as you pay for the dumps you want to get, you will get it immediately, CMAA Test Construction-Manager Dumps Pdf They get to know about their weak points and can make improvement accordingly before taking the real exam, In other words, your investments with Lead2PassExam Construction-Manager Certification Cost Links to an external site.
If users use the phone to retrieve their voicemails, Construction-Manager a port is required, People equate a fixed rate with a safe and secure investment, In this way, you don’t have to worry about Study Guide Construction-Manager Pdf the problem that you may not have enough time to make preparations for the tests.
Free PDF 2025 Latest CMAA Construction-Manager: Test Certified Construction Manager (CCM) Dumps Pdf
As long as you pay for the dumps you want to get, you will get Construction-Manager Downloadable PDF it immediately, They get to know about their weak points and can make improvement accordingly before taking the real exam.
In other words, your investments with Lead2PassExam Links to an external site, And as we can claim that as long as you study with our Construction-Manager learning guide for 20 to 30 hours, then you will pass the exam as easy as pie.
- Construction-Manager Latest Braindumps Book 🐛 Valid Construction-Manager Test Sample 🤷 Construction-Manager Test Dumps Demo 🤹 Search for ⮆ Construction-Manager ⮄ and download it for free on ☀ www.examcollectionpass.com ️☀️ website 📺Construction-Manager Test Dumps Demo
- Test Construction-Manager Questions Fee 🗻 Trustworthy Construction-Manager Exam Torrent 🦆 Construction-Manager Free Practice 🎪 Open website ➤ www.pdfvce.com ⮘ and search for “ Construction-Manager ” for free download 🦲Construction-Manager Testking Learning Materials
- Construction-Manager Answers Free 🐏 Construction-Manager Latest Braindumps Book 🧩 Exam Construction-Manager Certification Cost 🥣 Simply search for [ Construction-Manager ] for free download on “ www.troytecdumps.com ” 💟Construction-Manager Test Dumps Demo
- 100% Pass 2025 CMAA Construction-Manager: Test Certified Construction Manager (CCM) Dumps Pdf 🐦 Open ➽ www.pdfvce.com 🢪 and search for [ Construction-Manager ] to download exam materials for free 🥽Construction-Manager Pdf Free
- Construction-Manager Test Dumps: Certified Construction Manager (CCM) - Certified Construction Manager (CCM) Questions - Answers 🚘 Search on 《 www.vce4dumps.com 》 for ▷ Construction-Manager ◁ to obtain exam materials for free download 🚗Reliable Construction-Manager Test Topics
- Free PDF Quiz 2025 Perfect Construction-Manager: Test Certified Construction Manager (CCM) Dumps Pdf 📉 ⏩ www.pdfvce.com ⏪ is best website to obtain 「 Construction-Manager 」 for free download ⚔Valid Braindumps Construction-Manager Ebook
- Authentic CMAA Construction-Manager Exam Questions with Accurate Answers ⛅ Search for ☀ Construction-Manager ️☀️ on ➽ www.vce4dumps.com 🢪 immediately to obtain a free download 🤹Construction-Manager Test Dumps Demo
- Construction-Manager Test Dumps: Certified Construction Manager (CCM) - Certified Construction Manager (CCM) Questions - Answers 🚣 Easily obtain ➥ Construction-Manager 🡄 for free download through ☀ www.pdfvce.com ️☀️ ✅Construction-Manager Exam Material
- 2025 Test Construction-Manager Dumps Pdf - CMAA Certified Construction Manager (CCM) - Trustable Construction-Manager Certification Cost ❕ Open 「 www.examcollectionpass.com 」 and search for ➠ Construction-Manager 🠰 to download exam materials for free ⚠Latest Construction-Manager Real Test
- Latest Construction-Manager Real Test 😕 Trustworthy Construction-Manager Exam Torrent 🔲 Construction-Manager Reliable Exam Registration 🍴 Search for ☀ Construction-Manager ️☀️ and download it for free on ▛ www.pdfvce.com ▟ website 🖊Valid Construction-Manager Test Sample
- Latest Construction-Manager Exam Labs 🕣 Construction-Manager Test Dumps Demo 🤫 Valid Construction-Manager Test Sample 🎤 Open website { www.prepawaypdf.com } and search for ☀ Construction-Manager ️☀️ for free download 🔮Reliable Construction-Manager Test Topics
- ilearn.kennxl.com, www.stes.tyc.edu.tw, ncon.edu.sa, erp.thetechgenacademy.com, academy.wassimamanssour.com, yu856.com, www.stes.tyc.edu.tw, pct.edu.pk, www.stes.tyc.edu.tw, www.stes.tyc.edu.tw, Disposable vapes